A.
At a minimum you should require the contractor to provide a signed pile log, which needs to contain:
1. Project name and location
2. Name of contractor’s foreman or representative who witnessed the installation.
3. Date and time of installation
4. Location and reference number of each pile.
5. Description of lead section and extensions installed
6. Overall depth of installations referenced from bottom of grade beam or footing
7. Torque reading for the last three feet of installation if practical. In lieu of this requirement the termination torque shall be recorded as a minimum.
8. Any other relevant information relating to the installation.
9. Name of factory trained and certified technician and expiration date.
|